Sunday, July 31, 2022
July Construction
Friday, July 1, 2022
June Construction
I only got part way through what I was planning to accomplish in June. There were too many other things to take care of the last part of the month. I did complete the backdrops and most of the sub roadbed. The benchwork sections are bolted together.
I found that I will need to cut out at least two more 30-inch radius quarter sections and maybe a third. These will be for the town at the end of the line and/or where the track will pass over the interchange line as it goes to the mid-point town. I will also need to cut risers for the highest loop.
I have also been experimenting with different arrangements of the yard and engine service facilities tracks. The engine house and service facilities will be moving to the left end of the yard. this will help protect the buildings.
The lift-out sections between the two halves of the railroad use door hinges to hold them in place and keep the tracks aligned. Only one hinge for each end of the lift-outs is needed.
Some photos of the bench work and sub roadbed. Also, the latest track plan.
Revised yard area
The engine house (outlined building and sand house and fuel dock have been moved to the left end of the yard. The caboose track is now at the front. The team track has also been moved to the left of the new station location.
layout update
Due to the high temperatures experienced during the summer and early fall months, I didn't do much in the garage. Instead I assembled a...
-
While I am slowly working on the wiring for the main standard gauge layout, I started working on an HOn3 switching layout. There have bee...
-
Wiring is progressing. I have connected all the feeders to the buss for the staging tracks and two lift outs. control panels for the lift...